Building on the past for the future
The new development spans 4,000 square metres of PC2 laboratory and supporting workspace, replacing existing campus buildings that have reached the end of their life and creating modern, purpose-built facilities to support PHF Science (the New Zealand Institute for Public Health and Forensic Science) and its future research activities. The project also includes the demolition of approximately 7,200 square metres of existing facilities.
Rubix is providing full project management and Engineer to the Contract services for the project. Since construction commenced in 2024, we have worked closely with PHF Science's Business Manager and Property and Facilities Director, alongside Rau Paenga, providing advice to the Executive team and PHF Science Board throughout project delivery.
Key Challenges and Priorities
A key priority has been supporting effective governance and decision-making through advice and reporting to the PHF Science Board, while working closely with the project team to guide the design and delivery of the new facilities. The project has also required careful consideration of staging and delivery approaches to enable ongoing operations to continue across the site throughout the development process.
Delivery within a Crown Research Institute environment operating under Ministry of Business, Innovation and Employment (MBIE) approvals has required close coordination with stakeholders and advisors, including Rider Levett Bucknall (RLB) to provide budgeting and cost advice throughout design. The procurement of a construction partner within a highly active Wellington construction market was also a significant focus of the project.
Project renders courtesy of Warren and Mahoney.
Points of Interest
- Meaningful engagement with local iwi Ngāti Toa Rangatira has helped shape both the cultural significance of the site and the purpose of PHF Science.
- The design reflects this iwi engagement, giving the building an identity and sense of place that extends well beyond its functional brief.
- The facilities have been designed to support new ways of undertaking science research, both now and into the future.
- The project included the development of a procurement strategy tailored to current market conditions while operating within MBIE requirements.